Search This Blog

Saturday 31 May 2014

Bricklaying..Electrical & Plumbing...[Week7]

Last week, our wrap around the house has completed. Brick laying is half way.
Rough Electrical & Plumbing works are done and also ducted heating rough ins also done.
Also our landscape window in the kitchen is installed ! :-) So far happy with all the progress and looks ;-)
Also, our neighbor has installed fencing on one side...
Doors also have arrived...so I believe coming week, they might be installed...

Fencing

Porch

Ducted Heating

Landscape window in kitchen

Kitchen rough plumbing done

Bricks on our garage

Tuesday 20 May 2014

Frames are UP, Roofing almost Done..House is Finally visible ! :-) [WEEK 6]

I believe there is not much explanation needed for these...We STEPPED INTO our HOME for the very FIRST time...and it was a wonderful experience...Here are a few pics showing the current status out of the 70 odd pics which we took today !! :-D

Porch & Main Bedroom

Porch & Garage

Backyard

Garage


Laundry and Kitchen area

View from Kitchen / Living area through to the front



Our Home :-)
Manu

Monday 12 May 2014

Slab Pour and Frames Arrival ! [WEEK 4]

As on 8th May 2014

I did pop in today and guys are already working on Frames, after the slab pour finished last week ! I hope the frames will be finished by EOW.

Manu